Thames Water revises blueprint for Oxfordshire mega-reservoir
The Guardian reports that Thames Water has updated plans for its Oxfordshire site as costs reach up to £7.5bn.
The short version
- Thames Water has updated its proposal for the White Horse mega-reservoir near Abingdon, Oxfordshire, following cost increases and local opposition.[The Guardian]
- The site is expected to hold 150 billion litres of water, with estimated construction costs climbing from £2.2bn to between £5.5bn and £7.5bn.[The Guardian]
- Multiple local councils have rejected the plans, pointing to flood risks for neighbouring villages due to required river diversions.[The Guardian]
- Thames Water plans to submit its formal planning application in late 2026 to address a regional water deficit projected for 2055.[The Guardian]
Key facts
- Thames Water updated its design blueprint for the planned White Horse mega-reservoir near Abingdon, Oxfordshire.[The Guardian]
- The reservoir's estimated cost increased from £2.2bn to between £5.5bn and £7.5bn.[The Guardian]
- The planned facility will store 150 billion litres of water and cover an area of 6.7 square kilometres.[The Guardian]
- Oxfordshire County Council, Vale of White Horse District Council, and Abingdon Town Council rejected the project due to flood risks.[The Guardian]
- Infrastructure oversight body Rapid forecasted a water shortfall exceeding 2 billion litres per day by 2055.[The Guardian]
What remains uncertain
- Campaigners allege Thames Water has systematically underestimated final construction costs and overstated the project's strategic value.[The Guardian]
- Local community groups claim the utility company failed to conduct adequate consultation with residents and local bodies.[The Guardian]