North Yorkshire Council permits extraction of Drax ash mound

BBC News reports that Drax Power Ltd received approval to extract ash under restricted operating hours.

The short version

  • North Yorkshire Council approved plans by Drax Power Ltd to remove up to 23.5 million tonnes of ash near Drax Power Station.[BBC News]
  • Extraction operations are scheduled to run until 2045, followed by full site restoration by 2055.[BBC News]
  • Following local concerns over dust and noise, planners restricted operating hours and required 65% of the material to move by rail.[BBC News]

Key facts

  • Drax Power Ltd received planning approval to extract up to 23.5 million tonnes of ash from a disposal site adjacent to Drax Power Station.[BBC News]
  • Site extraction is set to continue until 2045, with restoration planned to conclude by 2055.[BBC News]
  • Work on the site is restricted to 08:00 to 20:00, excluding Sundays and bank holidays.[BBC News]
  • A planning condition requires 65% of the extracted ash to be moved via rail, with the remainder carried by road.[BBC News]