Tasmanian council approves 288MW datacentre despite local opposition and pending federal rules
George Town council voted 6-1 to grant planning permission for a major AI facility, citing current statutory constraints ahead of planned federal regulation.
The short version
- George Town council approved Firmus's proposed 288 megawatt AI datacentre at Long Reach, Tasmania, in a 6-1 vote, despite community backlash.
- Local objectors argued the council should delay approval until new federal rules take effect, but councillors noted they were bound by existing planning laws.
- Residents who submitted objections have a 14-day window to appeal the local planning decision.
- The decision comes as the federal government plans to establish nationwide datacentre standards for energy, water, and land use starting early next year.
Key facts
- The George Town council voted 6-1 to approve developer Firmus's plans for a 288MW AI datacentre at Long Reach, Tasmania.[The Guardian]
- The project site is located on the former Gunns Pulp Mill property near the Tamar River.[The Guardian]
- Over 300 public submissions were made regarding the proposal, alongside an online petition against the project that gathered nearly 6,000 signatures.[The Guardian]
- Prime Minister Anthony Albanese announced plans to legislate a nationally consistent regulatory framework for large datacentres starting early next year.[The Guardian]
- Objectors to the George Town council's planning decision have 14 days from Tuesday to file an appeal.[The Guardian]
- The Australian Energy Market Operator reported that 225 datacentres are currently in development across the country.[The Guardian]
- Victoria's Environment Protection Authority issued its first-ever objection to a datacentre over noise concerns regarding a proposed 366MW facility in Campbellfield.[The Guardian]
What remains uncertain
- It is unconfirmed whether community members will formally lodge appeals within the 14-day window, though organizers indicated multiple appeals are likely.[The Guardian]